64" Pipeline Design & Installation Support
Overview
This project involved supporting the design and installation of a 64" diameter pipeline in coordination with the installation contractor, surveyor, and a 3D scanning provider. My role focused on refining the pipeline geometry based on updated site data and producing accurate fabrication-ready pipe lengths and alignment adjustments.

Issue & Engineering Approach
The initial design was based on legacy survey data, which was found to be inaccurate once field conditions were verified. This created a risk of cumulative fit-up errors across the pipeline due to tight coupling tolerances.
To address this, the design was updated using high-accuracy 3D scan data and field verification in coordination with the surveyor and installation contractor.
The process involved:
-
Integrating updated survey and 3D scan data into the design model
-
Refining pipe lengths, slopes, and support locations based on as-built conditions
-
Iteratively validating geometry through multiple field scan campaigns
-
Coordinating design adjustments with installation sequencing
A total of four different scans were used to progressively refine the installation:
-
Initial design validation, routing and lengths
-
Post pour confirmation of footing and support locations
-
Post-installation verification of installed pipe sections
-
Final confirmation of angles and lengths for remaining tie-in sections
Design & Coordination Updates
Given the tight installation tolerances, each pipe segment required precise fabrication control:
-
Pipe sections were detailed to exact cut lengths based on verified field geometry
-
Slope and alignment were adjusted to match actual installed conditions
-
Support locations were refined to match as-built structural constraints
-
Coordination with the contractor ensured installability within sequence constraints
Each pipe joint required careful control due to coupling tolerances of ±3/16" and 0.35° angular misalignment.

Outcome
The updated design and iterative scan-based approach enabled accurate fabrication and installation of pipeline segments within tight geometric tolerances.
Close coordination between surveying, scanning, and fabrication reduced the risk of misalignment and ensured successful fit-up across multiple installation stages.